Sept 2007 Status Report
Muslim Cemetery Improvement Project
Denton, Texas
Phase 1 Expenses - COMPLETED
- $74,966 raised in July of 2000.
- $52,500 spent on concrete roads (70% complete). (20,400 sq. ft completed @ $2.57
per sq. ft.) - click here for satellite picture of road
- $16,000 spent on water well drilling, installation and water dispensing area.
- $5,253 spent to install electricity.
- $7,275 spent on the geotechnical survey to identify the land suitable for burial, and to
identify the land to be used for concrete roads and parking lots.
Phase 2 Expenses - NEEDED
- $29,000 to complete remaining 9,200 sq. ft. concrete road.
- $6,500 to replace water well pump - COMPLETED on 9/5/07
- $30,000 to construct washrooms, restrooms, storage room, and septic system.
TOTAL FUNDS REQUESTED: $59,000
If you would like to make a donation on-line using a major credit card,
please click on the PayPal button below.
Or, if you would like to make a donation by check, please mail to the
address below:
Muslim Cemetery, Inc.
P.O. Box 2629
Denton, TX 76202
* NOTE: Donations to Muslim Cemetery, Inc. are tax deductible
and you will be mailed a receipt for your donation.